The process starts with a slab condition assessment. The installer checks for active cracks, low spots, and moisture, Marietta’s climate variation stresses slab-on-grade concrete seasonally, so a moisture check before overlay application is not optional. Cracks and voids get filled and allowed to cure before any overlay material is mixed, so the new layer does not bridge over unstable areas.
A bonding agent and primer coat go down next, giving the cementitious overlay a mechanical connection to the existing slab. Without this step, the overlay can delaminate under foot traffic. The self-leveling mix is then poured and spread using a gauge rake and spiked roller, allowing it to seek its own level across the floor.
Once cured, the overlay surface can be ground smooth, polished, or left as a base for a protective topcoat. Flatness and bond testing confirm the layer has adhered before any finish work begins. The installer documents the overlay thickness and materials used so you have a full record of what was applied to your floor.